Water Services & Clinical Plumbing
Incoming mains, storage tank and booster connections, with distribution to clinical outlets. Installations include wash hand basins, theatre scrub up troughs, accessible WCs and dirty utility slop hoppers.
HEALTHCARE
Temporary services and permanent mechanical installations across a phased healthcare development.
Explore our scope
01 / THE PROJECT
Pintec installed temporary water services for the first operational phase of Southend Community Diagnostic Centre while progressing the permanent mechanical and public health installation across the wider development.
Appointed by the M&E contractor on a supply and install basis, our package covers incoming water infrastructure, clinical plumbing, drainage, heating and chilled water distribution. The centre includes NHS diagnostic services, consulting rooms, theatres and staff facilities.
02 / OUR SCOPE
From incoming water and plant connections to distribution pipework and clinical outlets.
Our capabilitiesIncoming mains, storage tank and booster connections, with distribution to clinical outlets. Installations include wash hand basins, theatre scrub up troughs, accessible WCs and dirty utility slop hoppers.
Low temperature hot water (LTHW) and chilled water distribution serving fan coil units, heater batteries and MRI equipment, with threaded mild steel pipework and flanged prefabricated sections.
Fusion welded HDPE and solvent weld drainage installations, with cast iron used for modifications to drainage services.
Plant room pipework, valve sets and equipment connections. The agreed testing scope includes pressure testing services and air and pour testing drainage.
03 / PHASED DELIVERY
Pintec installed a temporary water heater and isolated part of the water distribution to supply the first phase’s sanitaryware.
The first phase services have been maintained while the permanent installation has progressed across the wider footprint.
WIDER WORKS
The LTHW Plant Room and pipework connections to four air handling units are installed. The wider package includes chilled water distribution from four rooftop chillers.
04 / PLANT & SYSTEMS
Full pipework installation, including the flow and return headers serving the heating distribution.
Installation CompletePipework, valve sets and final connections to the four air handling units serving the project.
Connections InstalledChilled water pipework from the roof serving the MRI installation and air handling units.
Pipework in ProgressPIPEWORK & JOINTING
LTHW PRIMARY PIPEWORK
Pintec developed the boiler and pipework arrangement, with measured layouts and spool drawings used for coordination, fabrication and installation.
Prefabricated flanged pipework installed at the boilers, following the project’s arrangement and spool drawings. Installation in progress · September 2026
05 / ON SITE